Industrial electrical, automation, robotics & mechanical solutions for Australian manufacturers(03) 9761 8500 · [email protected]
Automation & Engineering · Water

Water treatment plant electrical & controls

MCC, remote I/O and instrumentation for a new water-treatment plant — sensing integrated to PLC and commissioned.

Mobile Automation delivered the electrical and controls installation and commissioning for a new water-treatment plant at a Victorian manufacturing site — from schematics and switchboard manufacture to a commissioned control system.

Schematics, panel layout and MCC manufacture

Design came first.

  • Panel layouts, terminal schedules and schematics revised as the plant developed
  • Two enclosures joined into a single MCC with earth bar, door interlock and circuit breakers
  • Protective steel barrier fitted, with door cut-outs for the fan, vents and HMI
  • Remote I/O enclosure laid out, wired and tested

Power, cable routes and drives on site

Power came in from the main outside distribution board.

  • MCC set on its plinth and fed with four 95 mm mains and a 35 mm earth
  • Cable tray joined to existing runs on cantilever brackets and strut dynabolted down
  • 2.5 mm, 6 mm and 10 mm sub-circuits to ten variable speed drives, then shielded cable to each motor
  • 11-core and Dekoron instrument cable run to the compressor
  • Data cabling in separate conduit
  • Two motors reconnected to star and tested

Level, temperature and valve instrumentation

Instrument cabling ran clear of the pipework.

  • Tray extended from the main run to the cold-water storage tank
  • Shielded twisted-pair cable to the tank and pump sensors, numbered and terminated against the instrument tag list
  • Temperature controllers wired and configured, sensors fitted off at the hot and cold ends
  • Power and control to the solenoid valves under the tanks and the boiler burner control

Commissioning the PLC and verifying every input

Communications came first.

  • Patch leads run and terminated, the processor addressed over USB and Ethernet brought online
  • I/O racks and the remote rack configured and checked
  • As-installed wiring walked down against the schematics, to a written commissioning plan
  • Eight level senders at the MCC and two at the remote rack moved from digital to analogue input cards
  • Spare cores identified and 24 V sensor supplies extended
  • Feedback verified in the Allen-Bradley software

The results

  • Plant handed over commissioned, from schematics to running control system
  • Ten variable speed drives fed and proved from a single MCC
  • Every instrument terminated and verified against the tag list and schematics

Explore water & wastewater support

Call (03) 9761 8500Request a Quote