Industrial electrical, automation, robotics & mechanical solutions for Australian manufacturers(03) 9761 8500 · [email protected]
Electrical · Automation · Manufacturing

Packing line electrical installation for a plastics manufacturer

The electrical installation of a new packing and stacking line — machine supplies, relocatable operator stations and full power and data provisioning.

Mobile Automation delivered the electrical installation of a new packing and stacking line for a plastics extrusion manufacturer, working alongside the line supplier's installation team.

Stripping the old line out with the reusable parts intact

The old line came out before anything new landed.

  • Discharge conveyor marked up for dismantling in sections
  • Cables labelled before anything was disconnected from the main switchboard
  • Components and conveyors earmarked for reuse set aside
  • Redundant machinery and cabling scrapped

Setting the machines and overhead cranes to level

Everything was marked out from the new layout and set true.

  • Base and floor plates marked out, corner holes drilled for chemical anchors and the rest drilled once those were set
  • Nuts torqued only after the anchors had cured
  • Main posts levelled with a theodolite before crane posts, beams and braces were bolted up, torqued and paint-marked
  • Transport legs cut off as equipment landed
  • Trolley tracks, cross rails, maintenance walkway and destacker ladder fitted

Machine supplies and data through the pits and trenches

Power and data followed the existing pit run to the oven.

  • Unistrut brackets made up to carry 150mm cable tray through the pit to the oven
  • Cables pulled as the tray went in, with steel conduit where runs needed mechanical protection
  • Machine supplies in 6mm² orange circular cable to the 10A and 15A GPO circuits
  • Outlets looped in pairs and fed from adaptable boxes
  • 10mm² run to the three-phase cardboard-cutting machine
  • Cat6 from the server rack, fitted off both ends and tested
  • Laser sensor Ethernet lead fault-found and repaired

Fitting off around a layout still being finalised

Bracket and outlet positions were still being settled during erection.

  • Circuits run and tied in ready for fit-off, then completed once locations were confirmed
  • Operator control station relocation absorbed by extending runs through junction boxes, then re-terminating and retesting
  • Despatch office power and data, exterior floodlighting, high bays and emergency lighting delivered alongside the line build

The results

  • New packing and stacking line installed and fitted off with the line supplier's team
  • Cranes, walkway and destacker set to level, torqued and paint-marked
  • Cabinets fitted off and marked up on the electrical drawings

Explore industrial electrical services

Call (03) 9761 8500Request a Quote