Industrial electrical, automation, robotics & mechanical solutions for Australian manufacturers(03) 9761 8500 · [email protected]
Industrial Electrical · Project · Agriculture

Berry nursery electrical installation

A complete electrical installation across admin, laboratory and controlled grow-room buildings for a new berry nursery.

Mobile Automation delivered the complete electrical installation for a new Victorian berry nursery — admin, laboratory and controlled grow-room buildings — around a live construction program.

Temporary supply that moved with the build

Construction power went in first, then was reworked as the buildings rose.

  • 6 mm² two-core-and-earth from the temporary board to the site container
  • Run on conduit and catenary wire, terminated into a 32 A circuit breaker
  • Tested and walked through with the builder
  • Feed later isolated, pulled back to the electrical pit, run underground to a second pit and re-energised

Mains reticulated underground to each building

Permanent mains were trenched in and distributed across the site.

  • 100 mm conduit trenched with draw wires and warning tape, backfilled with crushed rock and compacted
  • Mains winched from the irrigation and tractor sheds to the new main switchboard
  • Feeds carried on to the admin, laboratory and mechanical-services boards
  • 240 mm² sub-main re-run along the fence line
  • 150 mm² mechanical-services mains terminated, tested and locked out until the board was finished

Boards, lighting and outlets brought up in sequence

Boards were energised only as far as the build allowed.

  • RCBOs prewired before the switchboards went up on unistrut beneath suspended dropper tray
  • Laboratory board breakers selected to suit the connected loads
  • Internal lighting and power circuits tested and energised
  • Exit, emergency and external circuits left isolated in connectors until fit-off
  • Grow rooms 1 to 3 held until the floors were complete
  • Eleven exterior lights assembled onto purpose-fabricated brackets
  • Pendant outlets made up with conduit, glands and stainless wire for the sandwich-panel cool, media and grow rooms

Cutting over to the new standby generator

The old set came out and the new generator was brought in.

  • Old generator's 150 mm² flexible mains isolated and removed
  • 240 mm² XF 110 SDI mains installed to parallel the existing set
  • Cables landed on the bottom of the 800 A circuit breaker
  • Auto-start and auxiliary supply cables terminated
  • Mains outage simulated to prove the auto-start sequence

The results

  • Admin, laboratory and grow-room buildings supplied from the new main switchboard
  • Switchboard schedules and RCD lists compiled as circuits were proved
  • Installation walked through with the inspector and submitted

Explore industrial electrical services

Call (03) 9761 8500Request a Quote